Schedule

For the design phase, the first assumption that it will take to complete this phase was 10 hours, the next estimate time was of 63 hours, however it took 43.5 hours to completed it. The estimated weeks to complete this phase is between 7 to 8 weeks starting for the 3rd week up to the 11th week of fall quarter. On the Appendix E is a picture of this schedule, the green boxes represent when the task is started and when is expected to end.
Documentation of 3d modeling the estimated time was of 52.5 hours, but it took 35.5 hours to completed it. This phase was done on the moth of October and November.
Parts construction and Device construction;
these two phases should be done at the end of the winter quarter and have a working device.
Test phases
should be done on the following quarter.

Schedule: Text
Spring%20qrt%201_edited.jpg
Schedule: Image
schedule1_edited.jpg
Schedule: Image
schedule2_edited_edited.jpg
Schedule: Image
schedule update.PNG